West Huntsville area file · July 2026
The Zierdt corridor is delivering homes while its next connections take shape.
Lake Forest ranked second citywide for 2025 housing permits. The corridor also has a completed arterial and greenway, a newly opened recreation center, a Martin Road project nearing completion, and a Miller Branch network whose phases still need careful labels.

West Huntsville's Zierdt corridor is a useful example of why “growth” needs more than one number. The 2025 housing record shows permits, completions, subdivision lots, and apartment phases moving at different speeds. The transportation record is equally layered: Zierdt Road is complete, Martin Road Phase II was still unfinished in June 2026, one public greenway is open, and another multi-phase path is still being documented and funded.
This file keeps the geography tight enough to be useful. It does not treat every District 5 project as part of Zierdt, and it does not combine a Planning Commission layout with a building permit or completed home.
The reporting boundary
For this article, “West Huntsville and Zierdt” is an editorial reporting area centered on Zierdt Road from Madison Boulevard to Martin Road, then west through named connections along Martin Road, Beadle Lane, Wall Triana Highway, and Swancott Road toward the airport and Wheeler National Wildlife Refuge. It includes Lake Forest and Edgewater tract-level housing data because the City's development review uses those areas to report activity around the corridor.
Projects farther west are included only when a public record places them on a directly connected street such as Martin, Wall Triana, Swancott, or Rabbit Lane. The Grove at Indian Creek near Jeff and Capshaw roads, for example, appears in the same District 5 planning roundup but is outside this file's corridor and is not counted here.
This boundary is not a subdivision, civic association, school zone, ZIP code, council district, floodplain, or city-limit claim. For an address, use the City's GIS map gallery and My Huntsville Services.
Lake Forest carried the strongest 2025 construction signal
The City's 2025 Development Review reported 277 new-housing units permitted in Census tract 112.01, labeled Lake Forest. That was the second-highest tract total in Huntsville, behind Wade Mountain. The report also named Lake Forest among the areas with increased housing-construction activity during the year.
Delivery was substantial but not identical to permits. Lake Forest recorded 242 newly constructed units receiving certificates of occupancy during 2025: 207 multifamily units and 35 single-family or townhome units. Edgewater tract 112.02 recorded one single-family completion.
A permit authorizes construction; a certificate of occupancy authorizes occupancy. Neither number establishes how many homes were listed, sold, leased, or occupied by residents at year-end. The 242-unit completion total also cannot be assigned to a single development without project-level certificate dates. Our citywide housing-completions analysis preserves that distinction across every tract.
Approved lots show the next layer of supply
Planning Commission approvals added another pipeline signal. The annual report lists 161 major single-family lots approved in Lake Forest tract 112.01 and 138 in Edgewater tract 112.02 during 2025. Those are among the five largest tract totals in the City's subdivision table.
Approved lots are not completed houses and do not all reach construction at once. Streets, utilities, final plats, permits, builder schedules, and market conditions still affect delivery.
Apartment records show two different stages
At December 31, 2025, the City's apartment table listed Inspire in Lake Forest tract 112.01 with 237 units approved and permitted but zero shown as built. The same review said boundary-plat approval was granted for the remaining 354 units of Martin Road Apartments, south of Martin Road and west of Zierdt Road.
Those entries cannot be added to the 242 tract completions as though they all opened in 2025. Inspire was a permitted-not-built row at year-end. The Martin Road figure was a Planning Commission approval for a remaining phase. The current citywide status of all 14 apartment projects is reconciled in our 2026 apartment pipeline.
The corridor's housing signal is strong because permits, completions, and approved future supply all appear in the record—not because they are the same thing.
April 2026 added more subdivision and zoning actions
The City reported several April Planning Commission decisions on connected western roads. Bradford Crossing received a 122-lot layout approval south of Martin Road and west of Wall Triana Highway. Greenbrier Preserve South / Heritage Park Phase 2 received a 43-lot approval south of Swancott Road and west of Rabbit Lane.
A separate Swancott action rezoned 47.19 acres south of Swancott Road and east of Rabbit Lane from Residence 1-B to Residence 2. A rezoning changes the allowed land-use framework. It does not by itself approve a final subdivision, issue building permits, or establish a construction date.
The three actions should not be collapsed into a single 165-lot count plus acreage. Two are layout approvals in different places; one is a zoning change. Future plats, permits, and certificates will show whether and when homes are delivered.
Area status board
Eight records, eight delivery stages
The current corridor includes completed assets, active construction, planning approvals, and funded future links.
| Place or project | Verified stage | What the record establishes | Next update trigger |
|---|---|---|---|
| Zierdt Road improvementsMadison Boulevard to Martin Road | Complete | Four-lane corridor project and its west-side multi-use path were accepted for maintenance in 2022. | Future maintenance, safety, or separate intersection project. |
| Zierdt GreenwayShelton Road to Martin Road | Open | City lists a 3.3-mile paved multi-use path. | Official map, access, closure, or extension update. |
| Martin Road Phase IIOld Jim Williams Road to Laracy Drive | Nearing completion | Two bridge lanes opened by June 12, ending the Trademark detour; City said the project was not complete. | Final completion and maintenance acceptance. |
| West Huntsville Recreation Center150 Martin Road SW | Open | 27,350-square-foot facility opened December 22, 2025; current hours and programs are published. | Program, access, or operating-hours update. |
| Miller Branch Phase IWall Triana / Beadle to Swancott | Described as existing | 2026 City source calls the Swancott trail the existing first phase; no separate opening record was located. | Current map, dedicated location page, or opening documentation. |
| Miller Branch Phase IISwancott toward Wheeler refuge | Funded / engineering | TAP funding and local match announced; later source describes 1.6 miles and no construction date. | Final engineering, ALDOT coordination, bid, construction start, or final length. |
| Bradford Crossing / Greenbrier Preserve SouthMartin, Wall Triana, Swancott, Rabbit | Layout approved | 122 lots and 43 lots received April 2026 Planning Commission approvals. | Final plat, infrastructure, permit, or certificate record. |
| Swancott rezoningSouth of Swancott, east of Rabbit | Rezoned | 47.19 acres moved from Residence 1-B to Residence 2. | Subdivision, site plan, permit, or construction action. |
Status reviewed July 22, 2026. “Existing,” “approved,” “permitted,” “under construction,” and “open” describe different evidence.
Zierdt is complete; Martin Road was still active in June
The Zierdt Road improvement project widened approximately 3.5 miles between Madison Boulevard and Martin Road to four lanes and added a 12-foot multi-use path on the west side. The City marked the project complete and accepted for maintenance in June 2022. A 2023 update said resurfacing had also addressed the final rough sections from Madison Boulevard toward Triana.
Martin Road Phase II follows a different timeline. The project page describes 1.6 miles of five-lane roadway from Old Jim Williams Road to Laracy Drive, with four-foot bike lanes and five-foot sidewalks on both sides. Construction began in April 2024 under a $14 million ALDOT-funded contract.
The newest City update reviewed here is June 12, 2026. It said two lanes on the bridge over Betts Spring Branch had opened, traffic could again flow to Wall Triana Highway, and the Trademark Drive detour was no longer required. It also explicitly said the project was not complete. “Nearing completion” is therefore the current status—not complete and not merely planned.
The recreation center has crossed the opening milestone
The West Huntsville Recreation Center opened December 22, 2025 at 150 Martin Road SW, just west of Zierdt Road. The 27,350-square-foot facility has two configurable indoor courts, a fitness center, multipurpose rooms, and four lighted outdoor pickleball courts. Unlike an announced housing phase or greenway extension, this facility has a ribbon-cutting record and current operating hours.
The open Zierdt path and the Miller Branch phases form different parts of the network
The City's current Zierdt Greenway page lists 3.3 miles of paved multi-use path from Shelton Road to Martin Road. It identifies destinations around Madison Boulevard, Town Madison, Toyota Field, and Edgewater and lists parking at the two Publix locations on Madison Boulevard and Zierdt Road.
Southwest of the corridor, Dallas W. Fanning Nature Preserve at 258 Old Jim Williams Road has more than 1.5 miles of trails. The long-range Miller Branch concept is intended to connect the preserve area, Zierdt and Beadle paths, the Singing River Trail in Triana, and trails at Wheeler National Wildlife Refuge. That nearly 30-mile future network is a completion vision, not a claim that 30 connected miles are open today.
Phase I is described as existing, but the documentation is incomplete
In January 2024, the City approved a 1.8-mile first phase running from Wall Triana Highway toward Swancott Road and following Beadle Lane for part of the route. The announced total was $962,500, with a $192,500 City share and the Metropolitan Planning Organization covering the remaining 80% through Transportation Alternatives Program funding.
The February 2026 Phase II announcement refers to an “existing trail” at Swancott Road, which supports treating Phase I as physically present. However, this review did not locate a separate City ribbon cutting, a dedicated current location page, or an updated length and access record for Phase I. The status board therefore reports exactly what the later source establishes and names the documentation still needed.
Phase II has two official length descriptions
The November 2025 grant action described Phase II as 1.36 miles of 12-foot-wide asphalt path from Swancott Road along Miller Branch Creek toward refuge trails. The newer February 2026 project announcement described the segment as 1.6 miles. It estimated the project at about $1 million, with $797,464 in TAP funding and a $199,366 City match.
The later 1.6-mile figure is used as the working length in this file, while preserving the earlier 1.36-mile record. Final engineering should resolve the discrepancy. No construction schedule had been announced because engineering and ALDOT coordination were still required.
What to watch next
Martin Road completion
The bridge opening removed the detour, but the City had not yet marked the full Phase II project complete. Final acceptance is the next clean milestone.
Miller Branch mapping and construction
Phase I needs a current access map or opening record. Phase II needs a final length, design, bid, and construction date. Until then, the two phases should not be presented as one fully open route.
Conversion of approvals into homes
Bradford Crossing, Greenbrier Preserve South, the Swancott acreage, Martin Road Apartments, and the 2025 Lake Forest/Edgewater lots all need later plat, infrastructure, permit, or certificate records. The next update will track each project separately rather than publish one oversized pipeline total.
Apartment delivery after the 2025 cutoff
Inspire was permitted but not shown as built at year-end. A current certificate or occupancy record—not the 2025 permit total—should determine when that status changes.
Primary sources
- City of Huntsville, 2025 Development Review, Tables R-1, R-6, S-1, S-2, and PH-1.
- City of Huntsville, April 2026 District 5 Planning Commission actions, May 8, 2026.
- City of Huntsville, Zierdt Road improvement completion record, updated June 17, 2022.
- City of Huntsville, Zierdt Road resurfacing update, May 18, 2023.
- City of Huntsville, current Zierdt Greenway location and length.
- City of Huntsville, Martin Road Phase II scope and contract status, updated August 8, 2025.
- City of Huntsville, Martin Road bridge and detour update, June 12, 2026.
- City of Huntsville, West Huntsville Recreation Center opening, December 22, 2025.
- City of Huntsville, current recreation center facilities and hours.
- City of Huntsville, Miller Branch Phase I approval, January 11, 2024.
- City of Huntsville, Miller Branch Phase II grant action, November 20, 2025.
- City of Huntsville, Miller Branch Phase II scope and funding, February 12, 2026.
- City of Huntsville, Dallas W. Fanning Nature Preserve.
- City of Huntsville, GIS map gallery.
This area file is informational. It does not define a legal neighborhood, verify a specific address, estimate property value, or replace current planning, permit, title, survey, school-boundary, flood, insurance, or service records.